Checks whether information that the Procurement Act 2023 and the Procurement Regulations 2024 require to be included in a notice is actually present in what the contracting authority published on Find a Tender. Every check cites the provision it comes from. Part of Procurement Act Watch.
Figures below count information absent from published data, which is not the same as a finding that an authority breached a duty. How to read these figures.
These count scored, currently measurable checks against the notices in the selected dates. Charts breaks the same figures down by requirement, notice type, value and month; Absent information lists the notices behind them.
Scored rules only, ranked by how often the required information was absent from a notice the requirement applied to. Rules whose evidence fields are never populated anywhere in the results are excluded — they appear on the Field coverage tab instead.
Share of applicable scored checks where the required information was absent. Notice types with fewer than 20 notices in the results are omitted, since a rate over a handful of notices is not informative.
Whether high-value contracts are published any better than small ones. Band boundaries follow the Schedule 1 threshold in force on the day the notice was published, because Schedule 1 was amended on 1 January 2026 and banding an eighteen-month corpus against one set of figures would misplace everything near the boundary. Bands describe a notice; they do not decide whether it was above the relevant threshold, since that turns on the authority's own type and the kind of contract.
| Value band | Notices | Complete | Checks applied | Absent items | Absence rate |
|---|
Whether completeness is improving as authorities settle into the regime. Read the earliest months with care: February 2025 is a part-month and volumes were low.
Absolute counts, so large publishers dominate. The By authority tab shows rates alongside volume.
One row per rule. "Applicable" counts only notices the requirement actually bites on: a direct award justification is not counted against a competitively awarded contract, and reg 34(2)(a) disapplies the open/competitive-flexible question for framework call-offs.
| Provision | Required information | Grade | Citation | Applicable | Absent | Rate |
|---|
Ranked by absent items. "Complete notices" counts notices where every scored requirement that applied was present — the cleanest single measure of an authority's publication quality.
| Organisation | Notices | Complete notices | Checks applied | Absent items | Absence rate |
|---|
Listed here are notices where at least one thing the Procurement Act 2023 or the Procurement Regulations 2024 require to be included in that notice type was not published. A notice appears only on a scored rule that is currently measurable: an indicator result is too weak to put an authority on this list, and a rule whose evidence field is never populated is a defect in this tool rather than a finding. Complete notices are still reachable from the chips below, so the counts here reconcile with the By authority and By value tables.
| Organisation | Type | Title | Published | Value | Absent | Which requirements |
|---|
The control on everything else here. Each rule tests several candidate fields, because Find a Tender does not document one canonical location for most of these. A rule reporting a high absence rate while every one of its candidate fields shows a nil fill rate is measuring the wrong field — that is a defect in this tool, not a finding about authorities, and such rules are excluded from the headline figures automatically.
| Rule | Candidate field | Notices tested | Populated | Fill rate |
|---|
A check reports that required information is absent from the published data. That is not by itself a finding that an authority breached a duty: some requirements are conditional, some information is lawfully withheld under s.94, and Find a Tender does not export every field the regulations mention.
Requirements that cannot be tested at all are listed with their reasons on the Rules and citations tab, so the gap between what the law requires and what this tool measures is visible.
Dates choose what is shown, not what is fetched. Notices are read from Find a Tender once and kept in this browser, so narrowing the dates is instant. Only dates that have never been read are fetched, and only when you widen the range past them. Field coverage is always measured across everything loaded, not just what is on screen, so the check on whether a rule is measurable does not weaken when you narrow the view.
The full catalogue, including the evidence fields each rule tests. Nothing is hidden: rules that cannot be tested at all are listed at the bottom with the reason.
These are real statutory requirements. They are not measured here, for the reasons given. Some are measured by other tools in the suite.
| Provision | Required information | Why it is not checked here |
|---|